PgMP Practice Exam - Quiz 3

Program Management Professional Practice Exam

55 Questions | Select the best answer for each question

Question 1
You are a program manager of the relocation of the headquarter office from the downtown to the industrial area. Some of the stakeholders are against the program and others are supportive of the program. As a program manager, what will you do first?
Question 2
Program management office (PMO) and Program management information system (PMIS) are very important elements in program management. PMO establishes consistent policy, standards, and training for the program. The program management information system (PMIS) consists of tools used to collect, integrate, and communicate the program information. The above elements are parts of --------------.
Question 3
You are a program manager for the construction of a new power plant program. The program charter is approved, and now you officially commence the program planning sub-phase. During this sub-phase, the governance structure is established, the initial program organization is defined, and a team is assembled to develop the program management plan. Within the above context, which of the following is least likely for an effective governance structure?
Question 4
You are a member of the selection committee to select the programs and projects that your organizations will pursuit next season. One of the selected programs is for socioeconomic changes. This program contains 3 projects and one subsidiary program. One of the projects for improving the level of behavior and morality in the neighborhood. In which of the following do you document the output/outcome of that project?
Question 5
You are a manager of a large program. The program contains 7 projects and 3 subsidiary programs. While you are discussing the benefits register with the key stakeholders, for a clear understanding of stakeholders, you should map the benefits to program components as in ----------
Question 6
Which of the following is logically linking components, milestones, and high-level activities necessary to deliver program benefits?
Question 7
Your company had been awarded a new program. You are the program manager of that program. The stakeholders don't know why the program will be pursued and they don't have any visibility about the program. Within the above context, what is the best document that will be used?
Question 8
You are a program manager of a new hospital which aims to improve the treatment procedures. The components have been initiated to achieve the program objectives and benefits. One of these components is for the construction of a modern nursery for the employee's babies. During the evaluation of these component benefits, the stakeholders are not agreeing about the value that will be delivered from this component. As a program manager, what is the reason for this problem?
Question 9
You are a member in the selection committee. The following data has been given:
Program A: Cost = 30,000,000 and CBR=0.8
Program B: Cost = 20,000,000 and CBR=0.5
Program C: Cost = 40,000,000 and CBR=0.7
Program D: Cost = 35,000,000 and CBR=1.5
What program will be selected?
Question 10
The stakeholders may be internal or external to the program and may have a positive or negative impact on the outcome of the program. Program and project managers need to be aware of the stakeholders' impact and level of influence to understand and address the changing environments of programs and projects. Within the above context, you decided to categorize the stakeholders' relationships to the program. Which of the following documents can help you?
Question 11
You are a program manager of a telecommunication program. The program contains 3 projects. Now your program is in the delivery phase and the earned value calculations are as per the given data. Within the above context, what is the situation of the program?
Question 12
Your program is in the delivery phase and three components need to start. You want to identify the component managers. What will you do?
Question 13
Kelly is a manager of an infrastructure program for her organization SDF Inc. During the planning meeting with the team, she is discussing a document that contains the boundaries of the program scope. Which of the following documents is she discussing?
Question 14
Your program contains 15 projects, 3 subsidiary programs, and program activities. While you and the component managers are in the meeting, you notice that one of the component managers is always not participating in the meeting discussion and setting silent all the time. What should you do first to know his point of view?
Question 15
You are discussing the program with an individual or a group that is required to drive changes through the organization so the operations can accommodate capabilities delivered by the program and to secure the available positive benefits and steward the handling of negative benefits. Who is that individual or group?
Question 16
While you are in the delivery phase, two of the component managers need the senior consultant who is working at the program level and after discussion with them, you discovered that they need the consultant at the same time. What should you do?
Question 17
In your program, you have defined key performance indicators and metrics for stakeholders and their desired engagement. As a program manager, what is the next step?
Question 18
You are a program manager of the construction of a new airport. You know that the Civil Aviation Authority is waiting impatiently for the airport. The delivery date of the airport after two days only. It's very important to deliver the program in time and any delay will irritate the client. The delivery is a major milestone for the program. The program performance was very good. But now you discovered technical points that can't be rectified before the delivery date. Within the above context, what will you do?
Question 19
In your program, you are preparing the stakeholder engagement plan. One of the key stakeholders informs you that you have to perform stakeholder analysis and planning before developing the stakeholder engagement plan. You agree with the key stakeholder. Within the above context, what will you do first?
Question 20
Your program is the construction of 15 buildings inside the university. While you are in the execution phase, the sponsor informed you to upgrade three existing buildings. What will you do first?
Question 21
You are defining and prioritizing the program components and their interdependencies to create .....
Question 22
You are a program manager of an important program for your company. Now you are in the initiation stage developing a milestone plan. Which of the following contains the above information?
Question 23
While you are identifying the program outputs and outcomes to provide benefits aligned with the organization's strategic goals and objectives, the sponsor asks you this question, when will the program strategic alignment be performed? Your answer is...
Question 24
You are analyzing the stakeholders information that you have collected through interviews, focus groups, and historical information. The information is about the stakeholders' influence and impacts on the program, about who influences whom, the relations between the stakeholders, and who are in conflict with whom. All this information will be documented in.......
Question 25
You are a manager of the construction of a new airport program in your city. Your program contains 11 projects and is now in the execution stage. While you are in a meeting with the sponsor, he requests you to provide the performance of the project managers by next week. Which of the following is most likely considered to do that?
Question 26
While you are in the delivery phase of your program which contains 10 projects and two subsidiary programs. The component managers are assigned early in the delivery phase. You noticed that some of them don't know how to interact with other components and don't know how to identify the issues, risks, and dependencies that may impact other program components. Within the above context, what will you do?
Question 27
One of the stakeholders submitted you a request to change some points in the program, you discussed that request with the stakeholder and you started the impact analysis of that request. You found that the request will impact the program scope, schedule, cost, and benefits. You submitted the change request with the analysis to the program governance board for approval. After three days the governance board replied with approval, immediately you documented the approval in the change log. Within the above context, what will you do next?
Question 28
Program stakeholder communication is at the heart of program stakeholder engagement. It is key to executing program endeavors and, ultimately, delivering benefits to the organization. This critical component is a vehicle for information sharing, negotiation, and collaboration among the program team members to drive program implementation efforts. Within the above context, who is accountable for the above?
Question 29
DSDS is a large organization in the production of steel. They want to increase productivity by the construction of a new factory. The management assigned you as a program manager for the construction of the new factory. Now you are in a meeting with your team identifying the impacts to the program components from overruns or underruns. In which phase are you?
Question 30
Your program is designed to produce a new generation of electric cars. While you are in the formulation sub-phase, the sponsor informs you that MeCa Company is planning to produce the same type of cars. Immediately you started the environmental analysis. Which of the following will you use?
Question 31
You are a program manager for the construction of the infrastructure of a new Village. After some analysis, you defined a misalignment between the components and the organization's strategic plan elements. Which of the following are the least significant elements in the organization's strategic plan?
Question 32
Your program is critical for your organization's investments. The sponsor informed you that all the high management focuses on this program and its performance, so you decided to increase the number of health checks. Which of the following can affect the number of the previous activities?
Question 33
You are the program manager of the construction of a high dam in your country. The program consists of 20 projects and 7 subsidiary programs. The program management plan has been approved. Now you are in the delivery phase, and many risks have been identified, some of these risks are from projects that may impact other components in the program. You have noticed that the project managers report to each other only about the risks that may impact other projects and the program which leads to delay the program. Which of the following can avoid that problem in the future?
Question 34
A key stakeholder request a change that may impact the schedule of the program, you captured the request in the change log, performed the impact analysis then take the decision on behalf of the program governance board. The key stakeholder refused your behavior and requested approval on the change request from the governance board. Which of the following will you submit to the key stakeholder to show him that you are right?
Question 35
A key stakeholder request a change that may impact the schedule of the program, you captured the request in the change log, performed the impact analysis then take the decision on behalf of the program governance board. In which phase are you?
Question 36
You are the program manager of a construction of an airport in your city. The program consists of 15 projects and 4 subsidiary programs. The program management plan has been approved. Now you are in the delivery phase, and many risks have been identified. You have noticed that the project managers report to you all the project risks that have caused you to be preoccupied with project risks and loss of time needed to manage the program. Which of the following can avoid that problem in the future?
Question 37
Kelly is a program manager of an advertisements program. Now she is in the delivery phase, and the program sponsor is worried about the current status of the program cost and benefits, within the above context, which of the following will she provide to the sponsor?
Question 38
Your organization had been awarded the construction of a new airport in your city. You are the program manager of that program. While you are in the delivery phase, you are informed that one of the projects in your program is misaligned with the organization's strategic plan due to some major decisions that have been taken by the organization's CEO. Within the above context, what will you do first?
Question 39
Which of the following options contain the direction of the program?
Question 40
Your organization had been awarded the construction of a new industrial city. You are the program manager of this program. Now you and your team are developing the business case and the potential initiation of a new program to respond to some operational issues with the deployed products. Which activities are you developing?
Question 41
You are assigned as a program manager for a new hospital program. Now you are in the delivery phase, one of the components is completed and you want to explain to the steering committee that this component is completed. How can you do that?
Question 42
You are a program manager of the HYC program. You completed the delivery phase and are now in the Closure phase that includes program activities necessary to transition program benefits to the sustaining organization and formally close the program in a controlled manner. Within the above context, which of the following is not included in program transition?
Question 43
DICKO TEC is an organization for information technology. They have been awarded one of the most important programs with the Ministry of finance. You are the program manager of this program and the customer is very happy with the program performance. Now you are in the closure phase and all the program benefits have been delivered. Within the above context, what will you do to transition the program?
Question 44
MANZI is a large construction company in the Middle East. You are the program manager for the construction of a new airport program. The program is complex and has 20 components. Now you are in a meeting with the portfolio manager discussing the framework in which the portfolio, program, and projects management are integrated to achieve the strategic objectives. Which one of the following options can provide the mentioned above framework?
Question 45
Your organization just awarded the construction of a new seaport. During the portfolio meeting, some of the members prefer to pursuit it as a project, while other members suggest pursuit it as a program to enhance the delivery of benefits. How can the program enhance the delivery of benefits?
Question 46
Mark is a program manager for the construction of a new road. He is discussing with the team the program benefits and outcomes. During the discussion, a team member asks about the return of investment that may help to fund the future benefits. Within the above context, which of the following can provide a visual of when the return on investment may help funds of future program benefits?
Question 47
Your company just awarded 15 projects, each project scope is "construction of a new factory", in the same industrial city. All factories are different and all will be funded and supported by the government. All projects material will be provided from Hitachi Japan, as a preferred vendor. Now, you are a program manager of an existing program and your manager requests your proposal on; how you will manage these projects. What is the best proposal?
Question 48
DEGA is a large organization in the production of steel. They what to increase productivity by the construction of a new steel factory. The management assigned you as a program manager for the construction of the new factory. During the planning sub-phase, the program sponsor got his annual vacation. Within the above context, who may assume the role of the program sponsor?
Question 49
You are a program manager of the construction of a new hospital. During the execution of the program, you have identified a delay in getting resources allocated to the program components. Within the above context, what is your action?
Question 50
X and Y are two programs in the same portfolio. You are the program manager of Program Y, which is not critical to the portfolio. You have a risk strategy in your program that needs a scarce resource. But this scarce resource was assigned to program X. Within the above context, what will you do?
Question 51
You are the program manager of the construction of the new airport extension in your city. Now you are in the delivery phase and one of your team informed you that many of the products and deliverables have been tested many times by the same test which leads to increase in the cost. As a program manager, what will you do first?
Question 52
You are a program manager of the construction of a new tower in your city. The program contains 4 projects (project 1 up to project 4). While the program was in the delivery phase, an identified risk (R1) of project 1 occurred. Within the above context and the given data, what is the remaining contingency reserve of the program?
Question 53
You are a program manager of the construction of a new road for your organization ASDDM Inc. During the meeting, you and the sponsor are discussing the level of confidence in the appraisal of the activity durations. In which phase are you working?
Question 54
During the delivery phase of your program, a program team member has reached you to inform you about new activities that can accelerate the program schedule. What will you do FIRST?
Question 55
The Program governance comprises the framework, functions, and processes by which a program is monitored, managed, and supported in order to meet organizational strategic and operational goals. The Governance board ensures that the program is performing well and is on track to achieve expected program benefits. Within the above context, which of the following is the best tool used by the governance board for this?